Baustelle des Terminals 3 in Frankfurt: Eröffnung wird verschoben.

Opening in 2025Frankfurt Airport delays Terminal 3

Frankfurt Airport had previously planned to put the new Terminal into operation in 2023. Due to the Coronavirus crisis, Terminal 3 will open two years later.

Top-Jobs

bwlv

Fluggerätmechaniker (m/w/d)

BWLV-Motorflugschule Hahnweide
Vollzeit
Kirchheim/Teck
Top jobs
Deutschland
Feste Anstellung
Flugschule
Pilatus Logo

Team Leader Account Management

Pilatus Flugzeugwerke AG
Vollzeit
Top jobs
Schweiz
Feste Anstellung
Flugzeughersteller
Hahnair Logo

Compliance Monitoring Manager (all genders)

Hahn Air Lines GmbH
Vollzeit
Düsseldorf
Top jobs
Deutschland
Feste Anstellung
Luftfahrt
Etihad Job

Captain A320

Etihad Airways
Vollzeit
Abu Dhabi
Top jobs
United Arab Emirates
Feste Anstellung

In May, the management of Fraport made a decision. «We are convinced that air traffic will grow again in the long term», said Chairman Stefan Schulte. This is why the work on Terminal 3 continues despite the Coronavirus crisis. The consequences of a halt to construction would be «enormous additional costs» and «massive technical and structural risks». And so the making of a new Terminal in the south of Frankfurt Airport is continuing.

However, there is a change of plan. The temporary closure of inner-European borders has partially limited the availability of materials and personnel, a spokesperson for the airport operator Fraport told German newspaper Echo. «This will lead to delays in individual construction phases.» Nevertheless, the main building will be completed in 2024.

Pier G to finish earlier

The opening of Terminal 3 will still be postponed. Initially planned for 2022 and later delayed to 2023, it will now open at an even later point in time. «The current target for the start of operations is the beginning of the summer season 2025», the spokesperson said in response to Echo.

The second construction phase with Pier G for low-cost airlines will be finished earlier though. The construction work is already well advanced and the completion of the construction work is expected «probably at the start of the summer flight schedule 2022». This area can accommodate five million passengers a year.

Space for 14 million additional passengers per year

In addition to a passenger hall, the new Terminal 3 comprises two piers and 24 gates with passenger bridges. The project will create an additional capacity of 14 million passengers per year, and 25 million when fully expanded. It is located about 2.6 kilometres south of Terminals 1 and 2. A 5.6 kilometre long railway line is being built to connect the three terminals.

Mehr zum Thema

Lufthansa-Flieger: Nicht nach Nirgendwo unterwegs.

Lufthansa will not offer flights to nowhere

Terminal 2 des BER: Ungenutzt spart es Geld.

New Berlin Airport delays Terminal 2 to 2021

Zug und Flugzeug: Wer bedient welche Strecke?

Will trains replace flights more quickly?

Airbus A380: The airline is not yet letting go of the aircraft, but chances are that it won't take off again.

Lufthansa leaves little hope for the Airbus A380

Video

lufthansa erster airbus a350 1000 erstflug 01
Der erste Airbus A350-1000 der deutschen Fluggesellschaft trägt den XXL-Kranich und hat nun erstmals den Boden verlassen. Noch sitzen aber keine Lufthansa-Piloten am Steuer.
Timo Nowack
Timo Nowack
Die abgestürzte Beechcraft im Maisfeld: Alle vier Personen haben überlebt.
In Wisconsin stürzt ein Kleinflugzeug in ein Maisfeld. Die ersten Helfer kommen nicht über die Straße, sondern mit dem Fallschirm aus einem anderen Flugzeug, das zufällig in der Nähe war.
Benjamin Recklies
Benjamin Recklies
dubai vertiport 22
Wie funktioniert ein Verkehrsmittel, das es bislang noch gar nicht im kommerziellen Betrieb gibt? In Dubai laufen die letzten Vorbereitungen für den Start von Flugtaxis. Skyports-Manager Gareth Wilson verrät, warum Passagiere gewogen werden, wie schnell der Check-in ablaufen soll und weshalb das Netz mit nur einem einzigen Evtol startet.
gerard al fil
Gérard Al-Fil