Boeing 777-9: Ground tests were successful.

Engine problemsBoeing 777X won't take off this year

The US aircraft manufacturer is no longer expecting the 777X to make its maiden flight in 2019, which means there is a real threat that deliveries will not start until 2021.

Top-Jobs

bwlv

Fluggerätmechaniker (m/w/d)

BWLV-Motorflugschule Hahnweide
Vollzeit
Kirchheim/Teck
Top jobs
Deutschland
Feste Anstellung
Flugschule
Pilatus Logo

Team Leader Account Management

Pilatus Flugzeugwerke AG
Vollzeit
Top jobs
Schweiz
Feste Anstellung
Flugzeughersteller
Hahnair Logo

Compliance Monitoring Manager (all genders)

Hahn Air Lines GmbH
Vollzeit
Düsseldorf
Top jobs
Deutschland
Feste Anstellung
Luftfahrt
Etihad Job

Captain A320

Etihad Airways
Vollzeit
Abu Dhabi
Top jobs
United Arab Emirates
Feste Anstellung

The ongoing grounding of the 737 Max not only brings Boeing a record loss but it also severely damaged the image of the US aircraft manufacturer. It would, therefore, be a very important step for the manufacturer not only to quickly get the green light for its Max but also to launch the new 777X on time. «While the company is still targeting late 2020 for first delivery of the 777X, there is significant risk to this schedule given engine challenges, which are delaying first flight until early 2020.» writes Boeing. These are two pieces of news in one sentence.

Maiden flight planned for late 2019

On one hand, Boeing is hoping for first deliveries by the end of 2020 - in the best case scenario - after Emirates and Lufthansa had previously planned for the summer of 2020. On the other hand, the company admits that the first flight will no longer take place this year. Boeing CEO Dennis Muilenburg commented in a telephone conference that he was disappointed about the delays, which were caused solely by engine problems, while the ground tests were running on schedule.

At the Le Bourget air show in June, Boeing's head of the passenger aircraft division, Kevin McAllister, explained that as a result of new engine problems, the first flight had been planned to take place later in 2019. At the show, David Joyce, head of the engine manufacturer GE Aviation, also stated that despite new difficulties he was expecting the maiden flight to take place in 2019. GE Aviation is developing the massive GE9X engine, which will power the Boeing 777X. However, the company must first resolve a problem: A component on the front of the engine's compressor wears out sooner than expected.

Lufthansa also has to wait

Due to the delay, Lufthansa will also have to wait longer. The German airline has ordered 20 jets of the larger variant 777-9 from Boeing. Just recently, Lufthansa wrote in a press release that it would be one of the first airlines worldwide to «receive their first Boeing 777-9 in summer 2020.»

This is now no longer the case.In response to the question from aeroTELEGRAPH on how Lufthansa is dealing with the delay, a spokesperson merely commented: «As Boeing announced today, the delivery of the first 777X is planned for the end of 2020. We are constantly in touch with Boeing and are of course adapting to this new situation.» They are excited to receive their first jet.

Mehr zum Thema

Airbus A350-1000 at the Paris Air Show

Airbus and Boeing struggle to sell their flagship widebodies

ticker-boeing-1

Boeing erhält Milliardenauftrag für neuen US-Navy-Kampfjet F/A-XX

Boeing 737 Max 8 im Hintergrund, Max 10 im Vordergrund: In der Bestellung ist es anders herum.

Boeing hat riesige 737-Max-Bestellung von Turkish Airlines jetzt sicher

Airbus A320 Neo wird bei Tarmac Aerosave zerlegt: Das Unternehmen erweitert seine Zerlegungskapazitäten.

Warum wenige Jahre alte Airbus und Boeing-Flugzeuge schon verschrottet werden

Video

Airbus A350 F Erstflug in Toulouse: Der Frachter war vier Stunden in der Luft.
Vier Stunden, 220 Gigabyte Daten und ein Start ohne elektronische Schutzfunktionen: Der Airbus A350 F ist zum ersten Mal geflogen. Was die Crew testete und was den Frachter besonders macht.
Benjamin Recklies
Benjamin Recklies
airbus a350 f erstflug 01
Am Dienstag ist der Airbus-A350-Frachter zum ersten Mal abgehoben. Ende 2027 will der Flugzeugbauer den ersten A350 F aus der Serienproduktion ausliefern. Zwei Kunden kommen für die Premiere infrage.
Benjamin Recklies
Benjamin Recklies
Timo Nowack
Timo Nowack
Ex-Swissair-Sprecher Urs Peter Naef: «»
Als die Nachricht vom Absturz vor Halifax eintraf, war das Krisenhandbuch der Swissair-Kommunikationsabteilung noch nicht fertig. Medienverantwortlicher Urs Peter Naef musste improvisieren - und zugleich die Angehörigen vor aufdringlichen Medien schützen. Seine wichtigste Lehre aus der Katastrophe: «Steh zu dem, was passiert ist, und zeig Flagge.»
Christopher Scheffelmeier
Christopher Scheffelmeier